greenhoney wrote:VESTED
these are the current projects undertaken by APWR which is due to be completed this and next year. if these goes according to time and plan, this should be a billion cap stock by next year end?
Power Plant Project of Hailun Biomass Power Generation Co.,Ltd.
Contract Price: 200,000,000.00
Expected Completion Date: July, 2009
Power Plant Project of Xianglong Biomass Power Generation Co.,Ltd.
Contract Price: 240,000,000.00
Expected Completion Date: September, 2009
Power Plant Project of New Energy Biomass Power Generation Co.,Ltd.
Contract Price: 250,000,000.00
Expected Completion Date: Janurary, 2010
Dadi Power Generation Project
Contract Price: 290,000,000.00
Expected Completion Date: December, 2009
Mailv Biomass Power Generation Co., Ltd.
Contract Price: 310,000,000.00
Expected Completion Date: November, 2009
Tailai New Energy Biomass Power Generation Co., Ltd.
Contract Price: 280,000,000.00
Expected Completion Date: November, 2009
Muling Biomass Power Generation Co., Ltd.
Contract Price: 248,000,000.00
Expected Completion Date: September, 2009
Senchuan Biomass Power Generation Co., Ltd.
Contract Price: 310,000,000.00
Expected Completion Date: November, 2009
Hengwang Thermal Power Energy Co.,
Contract Price: 2,000,000,000.00
Expected Completion Date: January, 2010
Gongqing Cement Plant Project, 1 M Ton/year, Vietnam,
Contract Price: 260,000,000.00
Expected Completion Date: September, 2009
Wind Power Energy Project, Bayan Nur, Inner Mongolia
Contract Price: 210,000,000.00
Expected Completion Date: December, 2009
Type of Operation: Interconnected grid
Tiexin Cement Waste Heat Project, Phase III
Contract Price: 150,000,000.00
Expected Completion Date: September, 2009
Shucheng Wanneng Biomass Power Generation Co., Ltd.
LContract Price: 260,000,000.00
Expected Completion Date: August, 2010
Signed Contract
Contract Price: 256,000,000.00
Expected Completion Date: August, 2010
PP9 plant in Thailand
Contract Price: 75 million US dollar
Expected Completion Date: October, 2011
PP10 plant in Thailand
Contract Price: 75 million US dollar
Expected Completion Date: October, 2012
IPP plant
Location: Bangkok
Contract Price: 300 million US dollar
Expected Completion Date: July, 2010
Sanmenxia New Energy Biomass Power Generation Co., Ltd.
Contract Price: 96,000,000.00
Expected Completion Date: September, 2010
Huaian Huapeng Biomass Thermal Power Co., Ltd.
Contract Price: 360,000,000.00
Expected Completion Date: December, 2010
Based on the data, are we able to prioritise which deals will materialise first, and book to earnings?
Appreciate your sharing.