Malaysia - Infra Projects, Building Materials etc
ECRL – a Hobson’s choice
Source: The Star
https://www.thestar.com.my/business/bus ... ns-choice/
ECRL will cost RM55bil.
China Communications and Construction Co (CCCC) is in control of the project.
China’s Exim Bank is forking out 85% of the funding for the 688-kilometre railway track and CCCC is the main contractor.
Staff from China constitute about one-fifth of the total 4,000-odd workforce engaged for the project so far. Apart from staff, materials, machinery and other equipment for the project are mostly coming from China.
The Malaysian government is to fork out the remaining 15% of the funding requirement, amounting to about RM8.25bil. In return, Malaysian companies are to get up to 40% of the jobs.
However, the actual amount to be given to Malaysian companies has not been finalised yet, even though some RM13bil of the RM55bil cost of the project has been drawn down.
The ECRL has come under heavy criticism for its cost of RM55bil, which translates to close to RM80mil per km. Other railway projects in Malaysia have so far averaged less than RM50mil per km.
Another RM10.5bil more is to be added on to the loan amount for fortification works along the railway track to prepare the alignment for a double track in the future.
Source: The Star
https://www.thestar.com.my/business/bus ... ns-choice/